2.1.2 Perform Feasibility Study

At any stage during (or after) the development of a Business Case, a formal Feasibility Study may be commissioned. The purpose is to assess the likelihood of a particular solution option’s achieving the benefits outlined in the Business
Case. The Feasibility Study will also investigate whether the forecast costs are reasonable, the solution is achievable, the risks are acceptable and/or any likely issues are avoidable.

2.1.3 Establish Project Charter

After the solution has been agreed and funding allocated, a project is formed. The Project Charter defines the vision, objectives, scope and deliverables for the project. It also provides the organization structure (roles and responsibilities)
and a summarized plan of the activities, resources and funding required to undertake the project.Finally, any risks, issues, planning assumptions and constraints are listed.