3.2 Glossary of Terms
The following definitions apply to terminology used within the Project Lifecycle:
Acceptance Management
The process by which deliverables produced by the project are reviewed and accepted by the customer as meeting their specific requirements
Acceptance Planning
The process of identifying the milestones, criteria and standards for the acceptance of project deliverables by the customer
Business Case
A document outlining the justification for the initiation of a project. It includes a description of the business problem (or opportunity), a list of the available solution options, their associated costs and benefits and a preferred option for approval
Change Management
The process by which changes to the project scope, deliverables, timescales or resources are formally defined, evaluated and approved prior to implementation
Communications Management
The process by which formal communications messages are identified, created, reviewed and communicated within a project
Communications Planning
The process of identifying the type and regularity of information to be provided to all project stakeholders to keep them informed of the progress of the project
Kind regards,
Manoj
To BE CONTINUED.................
Monday, January 31, 2011
Sunday, January 30, 2011
EFFECTIVE PROJECT MANAGEMENT(24) !!!!
2.4.2 Review Project Completion
The final activity undertaken on any project is a review of its overall success by an independent resource. Success is determined by how well it against the defined objectives and conformed to the management processes outlined in the planning phase. To determine performance, a number of questions are posed.
For example:
▪ Did it result in the benefits defined in the Business Case?
▪ Did it achieve the objectives outlined in the Project Charter?
▪ Did it operate within the scope of the Project Charter?
▪ Did the deliverables meet the criteria defined in the Quality Plan?
▪ Was it delivered within the schedule outlined in the Project Plan?
▪ Was it delivered within the budget outlined in the Financial Plan?
To determine conformance, a review is undertaken of the level of conformity of the project activities to the management processes outlined in the Quality Plan. The above results, key achievements and lessons learnt are documented within a Post Implementation Review report and presented to the Project Sponsor for approval.
Kind regards,
Manoj
To BE CONTINUED.................
The final activity undertaken on any project is a review of its overall success by an independent resource. Success is determined by how well it against the defined objectives and conformed to the management processes outlined in the planning phase. To determine performance, a number of questions are posed.
For example:
▪ Did it result in the benefits defined in the Business Case?
▪ Did it achieve the objectives outlined in the Project Charter?
▪ Did it operate within the scope of the Project Charter?
▪ Did the deliverables meet the criteria defined in the Quality Plan?
▪ Was it delivered within the schedule outlined in the Project Plan?
▪ Was it delivered within the budget outlined in the Financial Plan?
To determine conformance, a review is undertaken of the level of conformity of the project activities to the management processes outlined in the Quality Plan. The above results, key achievements and lessons learnt are documented within a Post Implementation Review report and presented to the Project Sponsor for approval.
Kind regards,
Manoj
To BE CONTINUED.................
Friday, January 28, 2011
EFFECTIVE PROJECT MANAGEMENT(23) !!!!
2.4 Closure
Following the completion of all project deliverables and acceptance by the customer, a successful project will have met its objectives and be ready for formal closure. Project Closure is the last phase in the project and must be conducted formally so that the business benefits delivered by the project are fully realized by the customer.
2.4.1 Perform Project Closure
Project Closure involves undertaking a series of activities to wind up the project, including:
▪ Assessing whether the project completion criteria have been met.
▪ Identifying any outstanding items (activities, risks or issues).
▪ Producing a hand-over plan to transfer the deliverables to the customer environment.
▪ Listing the activities required to hand over documentation, cancel supplier contracts and release project resources to the business.
▪ Communicating closure to all stakeholders and interested parties.
A Project Closure Report is submitted to the Customer and/or Project Sponsor for approval.
The Project Manager is then responsible for undertaking each of the activities identified within the Project Closure Report on time and according to budget.
The project is closed only when all activities identified in the Project Closure Report have been completed.
Kind regards,
Manoj
To BE CONTINUED.................
Following the completion of all project deliverables and acceptance by the customer, a successful project will have met its objectives and be ready for formal closure. Project Closure is the last phase in the project and must be conducted formally so that the business benefits delivered by the project are fully realized by the customer.
2.4.1 Perform Project Closure
Project Closure involves undertaking a series of activities to wind up the project, including:
▪ Assessing whether the project completion criteria have been met.
▪ Identifying any outstanding items (activities, risks or issues).
▪ Producing a hand-over plan to transfer the deliverables to the customer environment.
▪ Listing the activities required to hand over documentation, cancel supplier contracts and release project resources to the business.
▪ Communicating closure to all stakeholders and interested parties.
A Project Closure Report is submitted to the Customer and/or Project Sponsor for approval.
The Project Manager is then responsible for undertaking each of the activities identified within the Project Closure Report on time and according to budget.
The project is closed only when all activities identified in the Project Closure Report have been completed.
Kind regards,
Manoj
To BE CONTINUED.................
EFFECTIVE PROJECT MANAGEMENT(22) !!!!
Communications Management
Communications Management is the process by which formal communications messages are identified, created, reviewed and communicated within a project. The most common method of communicating the status of the project is via a Project Status Report. Each communication item released to the project stakeholders is captured within a Communications Register.
2.3.3 Perform Phase Review
At the end of the Execution Phase, a Phase review is performed. This is basically a checkpoint to ensure that the project has achieved its stated objectives as planned.
Kind regards,
Manoj
To BE CONTINUED.................
Communications Management is the process by which formal communications messages are identified, created, reviewed and communicated within a project. The most common method of communicating the status of the project is via a Project Status Report. Each communication item released to the project stakeholders is captured within a Communications Register.
2.3.3 Perform Phase Review
At the end of the Execution Phase, a Phase review is performed. This is basically a checkpoint to ensure that the project has achieved its stated objectives as planned.
Kind regards,
Manoj
To BE CONTINUED.................
EFFECTIVE PROJECT MANAGEMENT(21) !!!!
Procurement Management
Procurement Management is the process by which product is sourced from an external supplier. To request the delivery of product from a supplier, a Purchase Order must be approved by the Project Manager and sent to the supplier for confirmation. The status of the purchase is then tracked using a Procurement Register until the product has been delivered and accepted by the project team.
Acceptance Management
Acceptance Management is the process by which deliverables produced by the project are reviewed and accepted by the customer as meeting his/her specific requirements. To request the acceptance of a deliverable by the customer, an Acceptance Form is completed. The Acceptance Form describes the criteria from which the deliverable has been produced and the level of satisfaction of each criterion listed.
Kind regards,
Manoj
To BE CONTINUED.................
Procurement Management is the process by which product is sourced from an external supplier. To request the delivery of product from a supplier, a Purchase Order must be approved by the Project Manager and sent to the supplier for confirmation. The status of the purchase is then tracked using a Procurement Register until the product has been delivered and accepted by the project team.
Acceptance Management
Acceptance Management is the process by which deliverables produced by the project are reviewed and accepted by the customer as meeting his/her specific requirements. To request the acceptance of a deliverable by the customer, an Acceptance Form is completed. The Acceptance Form describes the criteria from which the deliverable has been produced and the level of satisfaction of each criterion listed.
Kind regards,
Manoj
To BE CONTINUED.................
Wednesday, January 26, 2011
EFFECTIVE PROJECT MANAGEMENT(20) !!!!
Risk Management
Risk Management is the process by which risks to the project (e.g. to the scope, deliverables, timescales or resources) are formally identified, quantified and managed during the project. A project risk may be identified at any stage of the project by completing a Risk Form and recording the relevant risk details within the Risk Register.
Issue Management
Issue Management is the method by which issues currently affecting the ability of the project to produce the required deliverable are formally managed. After completion of an Issue Form (and logging the details within the Issue Register), each issue is evaluated by the Project Manager and a set of actions undertaken to resolve the issue at hand.
Kind regards,
Manoj
To BE CONTINUED.................
Risk Management is the process by which risks to the project (e.g. to the scope, deliverables, timescales or resources) are formally identified, quantified and managed during the project. A project risk may be identified at any stage of the project by completing a Risk Form and recording the relevant risk details within the Risk Register.
Issue Management
Issue Management is the method by which issues currently affecting the ability of the project to produce the required deliverable are formally managed. After completion of an Issue Form (and logging the details within the Issue Register), each issue is evaluated by the Project Manager and a set of actions undertaken to resolve the issue at hand.
Kind regards,
Manoj
To BE CONTINUED.................
EFFECTIVE PROJECT MANAGEMENT(19) !!!!
Quality Management
Quality is defined as “the level of conformance of the final deliverable to the customer’s requirements”. Quality Management is the process by which the quality of the deliverables is assured and controlled for the project, using Quality Assurance and Quality Control techniques. Quality reviews are frequently undertaken and the results recorded within a Quality Register.
Change Management
Change Management is the process by which changes to the project’s scope, deliverables, timescales or resources are formally defined, evaluated and approved prior to implementation.
A core aspect of the Project Manager’s role is to manage change within the project successfully. This is achieved by understanding the business and system drivers requiring the change, documenting the benefits and costs of adopting the change and formulating a structured plan for implementing the change. To formally request a change it is often necessary to complete a Change Form. The change request details may then be recorded within a Change Register.
Kind regards,
Manoj
To BE CONTINUED.................
Quality is defined as “the level of conformance of the final deliverable to the customer’s requirements”. Quality Management is the process by which the quality of the deliverables is assured and controlled for the project, using Quality Assurance and Quality Control techniques. Quality reviews are frequently undertaken and the results recorded within a Quality Register.
Change Management
Change Management is the process by which changes to the project’s scope, deliverables, timescales or resources are formally defined, evaluated and approved prior to implementation.
A core aspect of the Project Manager’s role is to manage change within the project successfully. This is achieved by understanding the business and system drivers requiring the change, documenting the benefits and costs of adopting the change and formulating a structured plan for implementing the change. To formally request a change it is often necessary to complete a Change Form. The change request details may then be recorded within a Change Register.
Kind regards,
Manoj
To BE CONTINUED.................
EFFECTIVE PROJECT MANAGEMENT(18) !!!!
2.3.2 Monitor and Control
While the Project Team are physically producing each deliverable, the Project Manager implements a series of management processes to monitor and control the activities being undertaken.
An overview of each management process follows.
Time Management
Time Management is the process within which time spent by staff undertaking project tasks is recorded against the project. As time is a scarce resource on projects, it is important to record the time spent by each member of the team
on a Timesheet to enable the Project Manager to control the level of resource allocated to a particular activity.
A Timesheet Register provides a summary of the time currently spent on the project and enables the Project Plan to be kept fully up to date.
Cost Management
Cost Management is the process by which costs (or expenses) incurred on the project are formally identified, approved and paid. Expense Forms are completed for each set of related project expenses such as labor, equipment and materials costs. Expense Forms are approved by the Project Manager and recorded within an Expense Register for audit purposes.
Kind regards,
Manoj
To BE CONTINUED.................
While the Project Team are physically producing each deliverable, the Project Manager implements a series of management processes to monitor and control the activities being undertaken.
An overview of each management process follows.
Time Management
Time Management is the process within which time spent by staff undertaking project tasks is recorded against the project. As time is a scarce resource on projects, it is important to record the time spent by each member of the team
on a Timesheet to enable the Project Manager to control the level of resource allocated to a particular activity.
A Timesheet Register provides a summary of the time currently spent on the project and enables the Project Plan to be kept fully up to date.
Cost Management
Cost Management is the process by which costs (or expenses) incurred on the project are formally identified, approved and paid. Expense Forms are completed for each set of related project expenses such as labor, equipment and materials costs. Expense Forms are approved by the Project Manager and recorded within an Expense Register for audit purposes.
Kind regards,
Manoj
To BE CONTINUED.................
Wednesday, January 19, 2011
EFFECTIVE PROJECT MANAGEMENT(17) !!!!
2.3 Execution
The Execution phase is typically the longest phase of the project (in terms of duration). It is the phase within which the deliverables are physically constructed and presented to the customer for acceptance. To ensure that the customer’s requirements are met, the Project Manager monitors and controls the activities, resources and expenditure required to build each deliverable throughout the execution phase. A number of management processes are also undertaken to ensure that the project proceeds as planned.
2.3.1 Build Deliverables
This phase requires the physical construction of each deliverable for acceptance by the customer. The actual activities undertaken to construct each deliverable will vary, depending on the type of project (e.g. engineering, building development, computer infrastructure or business process re-engineering projects). Deliverables may be constructed in a ‘waterfall’ fashion (where each activity is undertaken in sequence until the deliverable is finished) or an ‘iterative’ fashion (where iterations of each deliverable are constructed until the deliverable meets the requirements of the customer). Regardless of the method used to construct each deliverable, careful monitoring and control processes should be employed to ensure that the quality of the final deliverable meets the acceptance criteria set by the customer.
Kind regards,
Manoj
To BE CONTINUED.................
The Execution phase is typically the longest phase of the project (in terms of duration). It is the phase within which the deliverables are physically constructed and presented to the customer for acceptance. To ensure that the customer’s requirements are met, the Project Manager monitors and controls the activities, resources and expenditure required to build each deliverable throughout the execution phase. A number of management processes are also undertaken to ensure that the project proceeds as planned.
2.3.1 Build Deliverables
This phase requires the physical construction of each deliverable for acceptance by the customer. The actual activities undertaken to construct each deliverable will vary, depending on the type of project (e.g. engineering, building development, computer infrastructure or business process re-engineering projects). Deliverables may be constructed in a ‘waterfall’ fashion (where each activity is undertaken in sequence until the deliverable is finished) or an ‘iterative’ fashion (where iterations of each deliverable are constructed until the deliverable meets the requirements of the customer). Regardless of the method used to construct each deliverable, careful monitoring and control processes should be employed to ensure that the quality of the final deliverable meets the acceptance criteria set by the customer.
Kind regards,
Manoj
To BE CONTINUED.................
Sunday, January 16, 2011
EFFECTIVE PROJECT MANAGEMENT(16) !!!!
2.2.9 Contract Suppliers
Although external suppliers may be appointed at any stage of the project, it is usual to appoint suppliers after the Project Plans have been documented but prior to the Execution phase of the project. Only at this point will the Project Manager have a clear idea of the role of the supplier and the expectations for his/her delivery.
A formal Tender Process is invoked to identify a short-list of interested suppliers and select a preferred supplier to meet the procurement needs of the project. The Tender Process involves creating a Statement of Work, a Request for Information and Request for Proposal to obtain sufficient information from each potential supplier to select a preferred supplier. Once a preferred supplier has been chosen, a Supplier Contract is agreed for the delivery of the requisite product.
2.2.10 Perform Phase Review
At the end of the Planning phase, a Phase review is performed. This is basically a checkpoint to ensure that the project has achieved its stated objectives as planned.
Kind regards,
Manoj
To BE CONTINUED.................
Although external suppliers may be appointed at any stage of the project, it is usual to appoint suppliers after the Project Plans have been documented but prior to the Execution phase of the project. Only at this point will the Project Manager have a clear idea of the role of the supplier and the expectations for his/her delivery.
A formal Tender Process is invoked to identify a short-list of interested suppliers and select a preferred supplier to meet the procurement needs of the project. The Tender Process involves creating a Statement of Work, a Request for Information and Request for Proposal to obtain sufficient information from each potential supplier to select a preferred supplier. Once a preferred supplier has been chosen, a Supplier Contract is agreed for the delivery of the requisite product.
2.2.10 Perform Phase Review
At the end of the Planning phase, a Phase review is performed. This is basically a checkpoint to ensure that the project has achieved its stated objectives as planned.
Kind regards,
Manoj
To BE CONTINUED.................
Friday, January 14, 2011
EFFECTIVE PROJECT MANAGEMENT(15) !!!!
2.2.7 Develop Communications Plan
Prior to the Execution phase, it is also necessary to identify how each of the stakeholders will be kept informed of the progress of the project.
The Communications Plan identifies the types of information to be distributed, the methods of distributing information to stakeholders, the frequency of distribution and responsibilities of each person in the project team for distributing information regularly to stakeholders.
2.2.8 Develop Procurement Plan
The last planning activity within the Planning phase is to identify the elements of the Project which will be acquired from external suppliers to the project. The Procurement Plan provides a detailed description of the Products (i.e. goods and services) to be procured from suppliers, the justification for procuring each product externally, as opposed to from within the business, and the schedule for procurement. It also references the process for the selection of a preferred supplier (“Tender Process”) and the process for the actual order and delivery of the procured products (“Procurement Process”).
Kind regards,
Manoj
To BE CONTINUED.................
Prior to the Execution phase, it is also necessary to identify how each of the stakeholders will be kept informed of the progress of the project.
The Communications Plan identifies the types of information to be distributed, the methods of distributing information to stakeholders, the frequency of distribution and responsibilities of each person in the project team for distributing information regularly to stakeholders.
2.2.8 Develop Procurement Plan
The last planning activity within the Planning phase is to identify the elements of the Project which will be acquired from external suppliers to the project. The Procurement Plan provides a detailed description of the Products (i.e. goods and services) to be procured from suppliers, the justification for procuring each product externally, as opposed to from within the business, and the schedule for procurement. It also references the process for the selection of a preferred supplier (“Tender Process”) and the process for the actual order and delivery of the procured products (“Procurement Process”).
Kind regards,
Manoj
To BE CONTINUED.................
Wednesday, January 12, 2011
EFFECTIVE PROJECT MANAGEMENT(14) !!!!
2.2.5 Develop Risk Plan
The foreseeable project risks are then documented within a Risk Plan and a set of actions to be taken formulated to both prevent each risk from occurring and reduce the impact of the risk should it eventuate. Developing a clear Risk Plan is an important activity within the planning phase as it is necessary to mitigate all critical project risks prior to entering the Execution phase of the project.
2.2.6 Develop Acceptance Plan
The key to a successful project is gaining acceptance from the customer that each deliverable produced meets (or exceeds) his/ her requirements. To clarify the criteria used to judge each deliverable for customer acceptance, an Acceptance Plan is produced. The Acceptance Plan provides the criteria for obtaining customer acceptance, a schedule of acceptance reviews within which customer acceptance will be sought and a summary of the process used to gain acceptance of each deliverable from the customer.
Kind regards,
Manoj
To BE CONTINUED.................
The foreseeable project risks are then documented within a Risk Plan and a set of actions to be taken formulated to both prevent each risk from occurring and reduce the impact of the risk should it eventuate. Developing a clear Risk Plan is an important activity within the planning phase as it is necessary to mitigate all critical project risks prior to entering the Execution phase of the project.
2.2.6 Develop Acceptance Plan
The key to a successful project is gaining acceptance from the customer that each deliverable produced meets (or exceeds) his/ her requirements. To clarify the criteria used to judge each deliverable for customer acceptance, an Acceptance Plan is produced. The Acceptance Plan provides the criteria for obtaining customer acceptance, a schedule of acceptance reviews within which customer acceptance will be sought and a summary of the process used to gain acceptance of each deliverable from the customer.
Kind regards,
Manoj
To BE CONTINUED.................
Tuesday, January 11, 2011
EFFECTIVE PROJECT MANAGEMENT(13) !!!!
2.2.4 Develop Quality Plan
Meeting the quality expectations of the customer is critical to the success of the project. To ensure that the quality expectations are clearly defined and can reasonably be achieved, a Quality Plan is documented. The Quality Plan:
▪ Defines what quality means in terms of this project
▪ Lists clear and unambiguous quality targets for each deliverable. Each quality target provides a set of criteria and standards which must be achieved to meet the expectations of the customer
▪ Outlines a plan of activities which will assure the customer that the quality targets will be met (i.e. a Quality Assurance Plan)
▪ Identifies the techniques used to control the actual level of quality of each deliverable as it is built (i.e. a Quality Control Plan).
Finally, it is important to review the quality not only of the deliverables produced by the project but also of the management processes which produce them. A summary of each of the management processes undertaken during the execution phase is identified, including Time, Cost, Quality, Change, Risk, Issue, Procurement, Acceptance and Communications Management.
Kind regards,
Manoj
To BE CONTINUED.................
Meeting the quality expectations of the customer is critical to the success of the project. To ensure that the quality expectations are clearly defined and can reasonably be achieved, a Quality Plan is documented. The Quality Plan:
▪ Defines what quality means in terms of this project
▪ Lists clear and unambiguous quality targets for each deliverable. Each quality target provides a set of criteria and standards which must be achieved to meet the expectations of the customer
▪ Outlines a plan of activities which will assure the customer that the quality targets will be met (i.e. a Quality Assurance Plan)
▪ Identifies the techniques used to control the actual level of quality of each deliverable as it is built (i.e. a Quality Control Plan).
Finally, it is important to review the quality not only of the deliverables produced by the project but also of the management processes which produce them. A summary of each of the management processes undertaken during the execution phase is identified, including Time, Cost, Quality, Change, Risk, Issue, Procurement, Acceptance and Communications Management.
Kind regards,
Manoj
To BE CONTINUED.................
EFFECTIVE PROJECT MANAGEMENT(12) !!!!
2.2.3 Develop Financial Plan
Similar to the Resource Plan, a Financial Plan is prepared to identify the quantity of money required for each stage in the project. The total cost of labor, equipment and materials is quantified and an expense schedule is defined which provides the Project Manager with an understanding of the forecast spending vs. the actual spending throughout the project. Preparing a detailed Financial Plan is extremely important as the project’s success will depend on whether or not it is delivered within the ‘time, cost and quality’ estimates for this project.
Kind regards,
Manoj
To BE CONTINUED.................
Similar to the Resource Plan, a Financial Plan is prepared to identify the quantity of money required for each stage in the project. The total cost of labor, equipment and materials is quantified and an expense schedule is defined which provides the Project Manager with an understanding of the forecast spending vs. the actual spending throughout the project. Preparing a detailed Financial Plan is extremely important as the project’s success will depend on whether or not it is delivered within the ‘time, cost and quality’ estimates for this project.
Kind regards,
Manoj
To BE CONTINUED.................
Sunday, January 9, 2011
EFFECTIVE PROJECT MANAGEMENT(11) !!!!
2.2.2 Develop Resource Plan
Immediately after the Project Plan is formed, it is necessary to allocate the resources required to undertake each of the activities and tasks within the Project Plan. Although general groups of resources may have already been allocated to the Project Plan, a detailed resource assessment is required to identify the:
▪ Types of resources (labor, equipment and materials)
▪ Total quantities of each resource type
▪ Roles, responsibilities and skill-sets of all human resources
▪ Items, purposes and specifications of all equipment resource
▪ Items and quantities of material resource.
A schedule is assembled for each type of resource so that the Project Manager can assess the resource allocation at each stage in the project.
Kind regards,
Manoj
To BE CONTINUED.................
Immediately after the Project Plan is formed, it is necessary to allocate the resources required to undertake each of the activities and tasks within the Project Plan. Although general groups of resources may have already been allocated to the Project Plan, a detailed resource assessment is required to identify the:
▪ Types of resources (labor, equipment and materials)
▪ Total quantities of each resource type
▪ Roles, responsibilities and skill-sets of all human resources
▪ Items, purposes and specifications of all equipment resource
▪ Items and quantities of material resource.
A schedule is assembled for each type of resource so that the Project Manager can assess the resource allocation at each stage in the project.
Kind regards,
Manoj
To BE CONTINUED.................
Saturday, January 8, 2011
EFFECTIVE PROJECT MANAGEMENT(10) !!!!
2.2 Planning
By this stage, the benefits and costs of the project have been clearly documented, the objectives and scope have been defined, the project team has been appointed and a formal project office environment established. It is now time to undertake detailed planning to ensure that the activities performed in the execution phase of the project are properly sequenced, resourced, executed and controlled.
2.2.1 Develop Project Plan
The first step is to document the Project Plan. A ‘Work Breakdown Structure’ (WBS) is identified, which includes a hierarchical set of phases, activities and tasks to be undertaken on the project. After the WBS has been agreed, an assessment of the effort required to undertake the activities and tasks is made. The activities and tasks are sequenced, resources are allocated and a detailed project schedule is formed. This schedule will become the primary tool for the Project Manager to assess the progress of the project.
Kind regards,
Manoj
To BE CONTINUED.................
By this stage, the benefits and costs of the project have been clearly documented, the objectives and scope have been defined, the project team has been appointed and a formal project office environment established. It is now time to undertake detailed planning to ensure that the activities performed in the execution phase of the project are properly sequenced, resourced, executed and controlled.
2.2.1 Develop Project Plan
The first step is to document the Project Plan. A ‘Work Breakdown Structure’ (WBS) is identified, which includes a hierarchical set of phases, activities and tasks to be undertaken on the project. After the WBS has been agreed, an assessment of the effort required to undertake the activities and tasks is made. The activities and tasks are sequenced, resources are allocated and a detailed project schedule is formed. This schedule will become the primary tool for the Project Manager to assess the progress of the project.
Kind regards,
Manoj
To BE CONTINUED.................
Friday, January 7, 2011
EFFECTIVE PROJECT MANAGEMENT(9) !!!!
2.1.4 Appoint Project Team
At this point the scope of the project has been defined in detail and the project team are ready to be appointed. Although a Project Manager can be appointed at any stage of the project, s/he will need to be appointed prior to the establishment of the project team. The Project Manager documents a detailed Job Description for each project role and appoints a human resource to each role based on his/her relevant skills and experience.Once the team are ‘fully resourced’, the Project Office is ready to be set-up.
2.1.5 Set up Project Office
The Project Office is the physical environment within which the team will be based. Although it is usual to have one central project office, it is possible to have a ‘virtual project office’ environment, with project team members in various locations around the world. Regardless of the location, a successful project office environment will comprise the following components:
▪ Location (either physical or virtual)
▪ Communications (telephones, computer network, email, internet access, file storage,database storage and backup facilities)
▪ Documentation (methodology, processes,forms and registers)
▪ Tools (for accounting, project planning and risk modeling).
2.1.6 Perform Phase Review
At the end of the Initiation Phase, a Phase review is performed. This is basically a checkpoint to ensure that the project has achieved its stated objectives as planned.
Kind regards,
Manoj
To BE CONTINUED.................
At this point the scope of the project has been defined in detail and the project team are ready to be appointed. Although a Project Manager can be appointed at any stage of the project, s/he will need to be appointed prior to the establishment of the project team. The Project Manager documents a detailed Job Description for each project role and appoints a human resource to each role based on his/her relevant skills and experience.Once the team are ‘fully resourced’, the Project Office is ready to be set-up.
2.1.5 Set up Project Office
The Project Office is the physical environment within which the team will be based. Although it is usual to have one central project office, it is possible to have a ‘virtual project office’ environment, with project team members in various locations around the world. Regardless of the location, a successful project office environment will comprise the following components:
▪ Location (either physical or virtual)
▪ Communications (telephones, computer network, email, internet access, file storage,database storage and backup facilities)
▪ Documentation (methodology, processes,forms and registers)
▪ Tools (for accounting, project planning and risk modeling).
2.1.6 Perform Phase Review
At the end of the Initiation Phase, a Phase review is performed. This is basically a checkpoint to ensure that the project has achieved its stated objectives as planned.
Kind regards,
Manoj
To BE CONTINUED.................
Thursday, January 6, 2011
EFFECTIVE PROJECT MANAGEMENT(8) !!!!
2.1.2 Perform Feasibility Study
At any stage during (or after) the development of a Business Case, a formal Feasibility Study may be commissioned. The purpose is to assess the likelihood of a particular solution option’s achieving the benefits outlined in the Business
Case. The Feasibility Study will also investigate whether the forecast costs are reasonable, the solution is achievable, the risks are acceptable and/or any likely issues are avoidable.
2.1.3 Establish Project Charter
After the solution has been agreed and funding allocated, a project is formed. The Project Charter defines the vision, objectives, scope and deliverables for the project. It also provides the organization structure (roles and responsibilities)
and a summarized plan of the activities, resources and funding required to undertake the project.Finally, any risks, issues, planning assumptions and constraints are listed.
Kind regards,
Manoj
To BE CONTINUED.................
At any stage during (or after) the development of a Business Case, a formal Feasibility Study may be commissioned. The purpose is to assess the likelihood of a particular solution option’s achieving the benefits outlined in the Business
Case. The Feasibility Study will also investigate whether the forecast costs are reasonable, the solution is achievable, the risks are acceptable and/or any likely issues are avoidable.
2.1.3 Establish Project Charter
After the solution has been agreed and funding allocated, a project is formed. The Project Charter defines the vision, objectives, scope and deliverables for the project. It also provides the organization structure (roles and responsibilities)
and a summarized plan of the activities, resources and funding required to undertake the project.Finally, any risks, issues, planning assumptions and constraints are listed.
Kind regards,
Manoj
To BE CONTINUED.................
Wednesday, January 5, 2011
EFFECTIVE PROJECT MANAGEMENT(7) !!!!
The following sections provide a more detailed description of each phase and list document templates which provide the Project Manager with guidance on how to complete each phase successfully.
2.1 Initiation
The initiation phase essentially involves the project ‘start-up’. It is the phase within which the business problem or opportunity is identified, the solution is agreed, a project formed to produce the solution and a project team appointed.
2.1.1 Develop Business Case
Once a business problem or opportunity has been identified, a Business Case is prepared. This includes:
▪ A detailed definition of the problem or opportunity
▪ An analysis of the potential solution options available. For each option, the potential benefits, costs, risks and issues are documented. A formal feasibility study may be commissioned if the feasibility of any particular solution option
is not clear
▪ The recommended solution and a generic implementation plan.
The Business Case is approved by the Project Sponsor and the required funding is allocated to proceed with the project.
Kind regards,
Manoj
To BE CONTINUED.................
2.1 Initiation
The initiation phase essentially involves the project ‘start-up’. It is the phase within which the business problem or opportunity is identified, the solution is agreed, a project formed to produce the solution and a project team appointed.
2.1.1 Develop Business Case
Once a business problem or opportunity has been identified, a Business Case is prepared. This includes:
▪ A detailed definition of the problem or opportunity
▪ An analysis of the potential solution options available. For each option, the potential benefits, costs, risks and issues are documented. A formal feasibility study may be commissioned if the feasibility of any particular solution option
is not clear
▪ The recommended solution and a generic implementation plan.
The Business Case is approved by the Project Sponsor and the required funding is allocated to proceed with the project.
Kind regards,
Manoj
To BE CONTINUED.................
Saturday, January 1, 2011
EFFECTIVE PROJECT MANAGEMENT(6) !!!!
Project Execution
This phase involves the execution of each activity and task listed in the Project Plan.
While the activities and tasks are being executed, a series of management processes are undertaken to monitor and control the deliverables being output by the project. This includes the identification of changes, risks and issues, the review of deliverable quality and the measurement of each deliverable being produced against the acceptance criteria.
Once all of the deliverables have been produced and the customer has accepted the final solution,the project is ready for closure.
Project Closure
Project Closure involves releasing the final deliverables to the customer, handing over project documentation, terminating supplier contracts,releasing project resources and communicating the closure of the project to all stakeholders.
The last remaining step is to undertake a Post Implementation Review to quantify the overall success of the project and list any lessons learnt for future projects.
Kind regards,
Manoj
To BE CONTINUED.................
This phase involves the execution of each activity and task listed in the Project Plan.
While the activities and tasks are being executed, a series of management processes are undertaken to monitor and control the deliverables being output by the project. This includes the identification of changes, risks and issues, the review of deliverable quality and the measurement of each deliverable being produced against the acceptance criteria.
Once all of the deliverables have been produced and the customer has accepted the final solution,the project is ready for closure.
Project Closure
Project Closure involves releasing the final deliverables to the customer, handing over project documentation, terminating supplier contracts,releasing project resources and communicating the closure of the project to all stakeholders.
The last remaining step is to undertake a Post Implementation Review to quantify the overall success of the project and list any lessons learnt for future projects.
Kind regards,
Manoj
To BE CONTINUED.................